May 2019 Update

Construction Update                                                                              

May 14, 2019

The Phase IV Team, General Contractor Cochise Tech and Development and Lizard Rock Architects have made great progress in the planning stages of the new sanctuary. We have completed the 100% review of the architects design and approved them. Lizard Rock Architects has a few details to finalize with the mechanical and Civil engineers. Our General Contractor is in the process of requesting 65 % bid requests from sub contractors and they anticipate feed back from the sub contractors by the end of May or the first week of June. When the bids are received our General Contractor and the Phase IV Team will compile the cost estimates to see if we will be within budget for the complete project. If we are within our budget then we will have Lizard Rock Architects proceed in developing the plans on CD’s per Cochise Counties request. We will then submit the plans to the county for review approximately end of July time frame. Once Cochise County approves the plans and issues our permit then our General Contractor will go out for finalized bids from the sub contractors.  Our prayer is the county reviewers will act promptly on the plans and they will go through the process of review in minimal time.  At this time we are still scheduling construction to start in the November – December time frame.

March 8, 2017 Update

The latest progress with our application for permit is very promising. We are anticipating submitting all of the requested documentation and architectural drawings to the Cochise County Planning and Zoning department by March 13. It is expected that the process, that must play out before a permit is granted, will be up to 6 months. Our anticipation of the permit is eclipsed by how blessed we’ve been by God’s tender guiding through this long process.

March 9, 2016 UPDATE

Hello Church Family, 

Update on where we are at on the building plans. The Phase IV Team met with the county engineering staff for a pre-submittal of the building plans on February 24th. It was a good meeting and the county engineers were very helpful in providing us on what we were lacking as far as documentation. We have several items to complete before we do our primary submittal to the county. Our Civil Engineer needs to complete the site drawings to show all of our parking areas. Now that we have a verbal agreement between the church and a homeowner to grant us an easement for the sewer run the Civil Engineer is completing the required drawings. We need to have a traffic analyze done also. We are currently working on getting bids for this. Our timeline to submit the building plans to the county along with all the required permits will be by the end of April. Also, you may have noticed that there is a new equipment shed behind the Adult building. The equipment shed will be textured to match the new building when it is constructed. Please continue to pray for this project in the way Holy Spirit leads you.

Blessings, 

Phase IV Team